The following water outages are scheduled for Tuesday, Feb 16th and Wednesday, Feb 17th for water main valve replacements associated with the Downtown Water Main Rehab Project. Affected customers are being notified with door hangers and phone calls.
Crews will work to restore service as quickly as possible. Updates will be posted on Twitter (@ChasWaterSystem) and Facebook.
After service is restored, some customers may experience discolored water. Let a cold water faucet run until the water is clear.
Tuesday, February 16, 2016
9:00 am - 5:30 pm
120 customers impacted
Rutledge Ave between Spring and Line, Humphrey Ct, Porter's Ct, Sires St from Rose to Bogard

Wednesday, February 17, 2016
9:00 am - 5:30 pm
100 customers impacted
Rose Lane and Ashe Street between Spring and Line